Installation Process:
Day One: Floor Preparation (shotblast), repair cracks and imperfections
Day Two: Grind repairs even with the floor and application of 100% solids epoxy primer
Day Three: Application of 100% solids epoxy
Day Four: Application of aliphatic pigmented polyurethane
Light foot traffic is allowable 48 hours after
the final coat. Vehicle traffic is allowed 7 days following
the final day of installation.